Sagewood Homes would like to inform each customer
about the building schedule of a home.  Scroll down this
page to see an example of a typical construction schedule
for a custom home.  The schedule includes most, but not
all, of the activities involved in the process of building a
new home.

The actual schedule of completion for your project will vary
based upon many factors including, but not limited to size
and degree of difficulty of the structure, site and weather
conditions, material and contractor availability, crew sizes,
effective scheduling and communication, and perhaps most
significantly, the number, and complexity of the changes you
will make to the original contract.

 

Sample Construction Schedule

1. Interview with builder
2. Discuss floor plans and specification
3. Pre-approve financing with bank
4. Start design of floor plans
5. Review and redline floor plans
6. Review specifications
7. Review and finalize floor plans
8. Review and finalize specifications
9. Review and finalize site plan
10. Soils Test for foundation
11. Print and approve final floor plans
12. Engineer the foundation and structural plans
13. Print construction drawings
14. Make copies of plans
15. Distribute plans out for bid
16. Receive bids
17. Finalize bids
18. Price the Home
19. Sign Contract
20. Schedule closing on construction loan
21. Walk lot with owner
22. Construction of Home begins
23. Stake lot-Survey
24. Set temporary electric pole
25. Install construction entrance
26. Stake position of home
27. Set water meter
28. Clear lot
29. Scrape lot for foundation
30. Set form boards for foundation
31. Fill forms with dirt
32. Plumbing grounds set
33. Dig beams in foundation
34. Make up foundation
35. Foundation inspected by engineer
36. Pour foundation
37. Strip form boards
38. Lumber delivery
39. 1st floor wall framing
40. Subfloor framing
41. 2nd floor wall framing
42. Frame roof
43. Install cornice material (exterior trim and siding)
44. Install exterior doors and windows
45. Prime exterior (paint)
46. Install sheathing
47. Install roof decking
48. Install fireplace box
49. Plumbing topout
50. Felt roof
51. Shingle roof
52. HVAC rough-in
53. HVAC set indoor units
54. Electrical rough-in
55. Install electric service panel
56. Alarm rough-in
57. Phone rough-in
58. Cable rough-in
59. Audio visual rough-in
60. Frame inspection
61. Frame punch
62. Brick veneer
63. Batt insulation
64. Caulk and air seal
65. Stock drywall
66. Hang drywall
67. Tape and finish drywall
68. Texture drywall
69. Trim lumber delivered
70. Install interior doors
71. Install interior trim
72. Install cabinetry
73. Prep drywall for prime coat
74. Prime paint drywall
75. Prep trim for prime coat
76. Prime trim
77. Finish coat trim
78. Paint exterior of home
79. Install fireplace mantel
80. Install tile floor
81. HVAC trim
82. Plumbing trim
83. Electrical trim
84. Install light fixtures
85. Install ceiling fans
86. Install kitchen counter tops
87. Install bath room counter tops
88. Alarm trim
89. Phone trim
90. Cable trim
91. Audio visual trim
92. Clean windows
93. Rough grade
94. Driveway
95. Patios
96. Porches
97. Sidewalks
98. Final grade
99. Set A/C units
100. Start up A/C units
101. Mirrors
102. Shower door
103. Door hardware
104. Bath hardware
105. Install wood floors
106. Rough interior clean
107. Caulk and prep interior for paint
108. Final coat of paint on drywall
109. Final coat of paint on trim
110. Install appliances
111. Trim fireplace
112. Install carpet
113. Interior clean
114. Install blinds
115. First paint touch up
116. Install gutters
117. Install sprinkler system
118. Install landscaping
119. Install sod
120. Adjust windows
121. Install screens
122. Final Inspection
123. First walk-thru
124. Final punch out
125. Punch out walk thru
126. Final paint touch up
127. Final interior clean
128. Final walk thru
129. Close at title company
130. Move into new Home